The Breck Athletic Complex is planned at Highway 164, Town Line Road and Skyline Avenue in the Village of Big Bend. This page shows you what that means: how big, how tall, how bright, how long. Every number comes from a public record.

The Army Corps of Engineers reviewed 149.79 acres for this project. A football field with end zones is about 1.32 acres. That's 113 of them, side by side.

"It's going to be the biggest in the area… probably almost the state."
Eric Weishaar, developer, Big Bend Plan Commission, Nov 20, 2025 (video 24:31)
"Baseball alone will be 170, almost 200 teams on a weekend."
Eric Weishaar, Plan Commission, Nov 20, 2025 (video 1:08:10)
"Maybe not quite on the level as like a DockHounds or a Milkman stadium, but a little bit more elevated, nicer seating, more amenities."
Eric Weishaar, Plan Commission, Nov 20, 2025 (video 22:20), describing the championship field
"…college teams that maybe want to have a game there… high school games."
Eric Weishaar, Plan Commission, Nov 20, 2025 (video 22:53)
The DockHounds and Milkmen are professional independent-league teams. WisDOT later wrote that nothing it knew of would prevent the expanded championship field from hosting an independent-league team, and required the traffic study to assume 2,500 seats. (WisDOT emails, Aug 31 and Sept 3, 2026.)
The lighting plan calls for 131 poles. Most field poles run 40 to 80 feet. Two championship poles are 90 feet, five feet over what the Village approved.

Six baseball fields, lighted batting cages, seven soccer and four lacrosse fields, and a championship field with seating to be scaled to 2,500. The developer expects 170 to 200 baseball teams on a weekend.
The site is surrounded by working farms and family homes on private wells. Its water drains toward the Mill Brook–Fox River watershed, which DNR recorded in its own field assessment. The Vernon Marsh Wildlife Area lies to the west.

About 4,300 acres of state wildlife area along the Fox River, west of the site, with two no-entry waterfowl refuges. The marsh sits near 755 ft. The Breck site sits on high ground near 935 ft, about 180 feet above it, and its light poles would rise another 90.



Over 3,000 homes in Vernon, Waukesha and Big Bend sit within three miles, with $2.35 billion in taxable property. Most of it is outside Big Bend, where residents get no vote on Breck.


Highway 164 is a state highway. Only the Wisconsin Department of Transportation can approve a new connection to it.
This parcel is restricted to no more than one access point to Highway 164.WisDOT, Development Review meeting, Jan 27, 2026. Signals, if warranted, go at Town Line or Skyline, not at the driveway.
We have not made a decision on whether the access will be allowed.WisDOT email, June 4, 2026
The developer has been told that WisDOT requires a public street connection … for the placement of a traffic signal or roundabout at any intersection with a State Highway.WisDOT written reply, Sept 8, 2026
There will be no construction access permitted to this site from WIS 164.WisDOT to ISG, May 12, 2026
A TIA has not been submitted.WisDOT written reply, Sept 8, 2026. WisDOT requested the Traffic Impact Analysis on May 12, 2026.
The current and projected operations in this section of WIS 164 are unacceptable.Intersection Control Evaluation for WisDOT, WIS 164 from County ES to the I-43 ramps, May 12, 2022
The developer's own estimate: 6,950 trips on a weekday and 9,160 on a Saturday at full build-out, with 1,880 in the Saturday peak hour. (ISG to DNR, Aug 5, 2026.)
WisDOT's finding: new trips "will increase the through volumes on WIS 164 by more than 20% for the PM and Saturday Peak Hours." (June 11, 2026.)
WisDOT rejected the developer's first traffic review with 12 comments, calling the trip distribution unrealistic and the championship-field estimate "very low."
The I-43 / Highway 164 interchange is scheduled for reconstruction in 2027.
The developer's consultant mapped seven wetlands in October 2025. The first state permit asks to fill part of one of them for a road.
DNR rated Wetland D's flood and stormwater storage HIGH on all 8 of 8 criteria (July 20, 2026). The fill is 0.86 acre of its 1.90 acres, about 45%.
A licensed engineer found about 62% of the site is Group D clay, the soil that sheds the most runoff. The developer's stormwater model listed it as 0.000 acres. Neighbors are challenging the stormwater permit in a contested case filed Sept 18, 2026.
The Village approved Breck without the studies that would show whether it is safe for the roads, the water and the neighbors. Those were left for later, as conditions. So we took it to court and to the state.
WisDOT asked for a Traffic Impact Analysis on May 12, 2026. None had been submitted as of Sept 8, 2026.
The approval defers final grading, drainage and stormwater plans to review "prior to issuance of any permits" (Condition 14). The Village Engineer asked in writing about the culverts that would receive the runoff; no answer appears in the records we obtained.
The approval adds a dark-sky condition, but no night-sky or light-spill study has been done for 881 fixtures on poles up to 90 feet.
A PA system is banned unless the Village Board approves one later. No noise study was done.
These cases cost money: court transcripts alone run about $3,000. Help fund the fight.
As of November 8, 2026.
| Approval | Agency | Status | Detail |
|---|---|---|---|
| Access to Highway 164 | WisDOT | Not approved | No decision; no Traffic Impact Analysis submitted. |
| Wetland fill, Wetland D | DNR | Pending | Docket IP-SE-2026-68-01785. Public hearing held Oct 6, 2026. |
| Construction stormwater | DNR | Issued | WI-S067831-06, Aug 19, 2026. Contested case filed Sept 18, 2026. |
| Federal wetland jurisdiction | Army Corps | Decided | Wetlands A–E found non-jurisdictional, June 25, 2026. |
| Conditional use permit (Stage 1) | Village of Big Bend | In court | Case 2026CV000978. Court expanded the record Oct 1, 2026. |
| Stage 2 expansion and zoning district | Village of Big Bend | In court | Approved Sept 24, 2026. Challenged in court, Oct 2026. |
| Land purchase | Private | Not closed | Conditional purchase agreement since September 2025. |
No. WisDOT asked for a Traffic Impact Analysis on May 12, 2026. As of September 8, 2026, none had been submitted.
The developer compared the championship field to the DockHounds' and Milkmen's stadiums and talked about college teams. WisDOT required traffic to be studied at 2,500 seats.
No one knows yet. There is no night-sky study. The poles stand 40 to 90 feet on high ground above the surrounding land.
No. The site borders Vernon, drains toward the Mill Brook–Fox River watershed, and its traffic uses Highway 164 and I-43. The Village of Waukesha Board sent a letter of opposition, read into the Big Bend record on Jan 29, 2026.
The Three Villages Association and the EndBreck Coalition are neighbors from Big Bend, Vernon and Waukesha. We read the filings, request the public records, and share what they say. Court transcripts, legal fees and expert review cost real money.
@Jackie-Trimborn
Account name: ThreeVillages Association. Add "EndBreck" and your village in the note.
Open in VenmoThree Villages Association U.A.
P.O. Box 25
Big Bend, WI 53103
Illustrations and the sound sample are labeled as such. If you find an error, tell us and we will correct it.